If you are planning a landed rebuild or addition and alteration (A&A) works, your Qualified Person (QP) will usually ask for a sewerage interpretation plan Singapore homeowners still look up by that name, together with a Drainage Interpretation Plan (DIP). PUB, Singapore’s National Water Agency, now officially calls the sewer plan a Sewerage Information Plan (SIP). Both are PUB Services Plans, purchased on the Singapore Land Authority (SLA) Integrated Land Information Service (INLIS) portal, not at a PUB counter.
The plans show where public sewers and drainage reserves sit in relation to your plot. They can change the house layout, the platform level, whether a sewer has to be diverted, and how close you can build to a drain. Your QP must still verify the actual alignments and levels on site before the design is locked in.
What SIP and DIP Are, and What PUB Calls Them
PUB’s PUB Services Plans page, and the same wording on the SLA INLIS PUB Plans product page, describe the two plans as follows.
A Sewerage Information Plan (SIP) indicates the location and alignment of public sewers or pumping mains in the vicinity of the development. Details of the existing sewer connections may not be shown. The QP should ascertain and verify those connection details on site.
A Drainage Interpretation Plan (DIP) indicates drainage reserves, or land reserved for future drainage schemes. Details of the common drain may not be shown. The QP should ascertain and verify the common drains on site, and the Minimum Platform Level (MPL) needed for effectual surface water drainage.
Homeowners and older notices often still say “sewerage interpretation plan” or “sewer interpretation plan”. PUB’s Code of Practice on Sewerage and Sanitary Works (3rd Edition, March 2025) and its 31 July 2026 circular use “Sewerage Information Plan”. The DIP name has not changed.
The same INLIS product also offers a Water Service Plan (WSP), which shows the approximate position of nearby water mains and raw water mains. Smaller submains and connection pipes under 100mm may not be included. None of these plans replaces a site survey. After the plans are received, the QP must verify on site the alignments and invert levels of the public sewers, pumping mains, sewer connections, drainage reserves, common drains and water mains.
Why a Landed Rebuild Needs These Plans
Public sewers, setbacks and diversion
Before design work starts, the Code of Practice on Sewerage and Sanitary Works requires the SIP to be obtained. The exact position, alignment and level of each affected sewer and pumping main must then be ascertained on site and shown on the submitted plan.
A public sewer on or near a landed plot can stop a house, basement, retaining wall or footing from sitting where you first hoped. No structure, object or building may be placed over or across any sewer or manhole without PUB’s approval, except for items the Code excludes, such as compound boundary walls, perimeter drains, and lightweight, demountable elements like decking, awnings, fencing, planting troughs and link-way shelters. Manholes must not be built inside a building or under any structure, or covered up or paved over, without PUB’s approval.
Permanent structures must also keep the Code’s minimum setback, measured from the outermost edge of the structure, including footings and overhangs, to the centreline of the sewer pipe or Deep Tunnel Sewerage System (DTSS). For a sewer or pumping main of 600mm diameter or smaller, that distance is 1.0m if the sewer is 3m deep or less, 1.5m if it is more than 3m and up to 5m deep, and 2.0m if it is deeper than 5m. Larger sewers and the DTSS have greater setbacks, calculated from the diameter. The full figures are in Table 1 of the Code of Practice on Sewerage and Sanitary Works (3rd Edition, March 2025).
If the rebuild cannot meet those rules, PUB’s approval must be sought to relocate the affected sewer, to co-locate it in a reinforced concrete (RC) trench that allows repair and maintenance, or to provide additional sewers. PUB may consider a diversion of an existing public sewer for better land use, carried out at the developer’s cost.
The SIP is also needed during construction. PUB’s advisory on preventing damage to the public sewerage system tells the contractor to purchase the SIP through SLA INLIS, display a copy at the site, and obtain written clearance through the PUB Protection of Water Pipes and Sewers (POWS) system before carrying out specified activities, such as excavation more than 0.5m deep or piling, inside a public sewer corridor. That corridor extends either side of the sewer centreline: 10m for sewers smaller than 900mm in diameter, 20m for sewers of 900mm or larger, and 40m for DTSS tunnels.
Existing sewer connections may not appear on the SIP. For a redevelopment, an existing drain-line that runs into a neighbouring premises should be discontinued where a direct connection to a public sewer in the public area is feasible. For detached or terrace houses on individual lots, each lot must have its own drain-line connection to the public sewer.
Drainage reserves, platform levels and crests
The DIP shows whether a drainage reserve, or land reserved for a future drainage scheme, affects the plot. The Code of Practice on Surface Water Drainage requires land set aside as a drainage reserve to be kept free of all encumbrances, and says no structure shall be constructed within a drain or drainage reserve. Embankments and structures must be set outside the drainage reserve. Structural and stability calculations for an embankment or structure within 2m of the edge of a drainage reserve must be endorsed by a Professional Engineer and submitted to PUB for record.
The DIP may not show the common drain. Your QP has to pick that up on site. The QP must also ascertain the Minimum Platform Level. PUB’s Services Plans page does not say the DIP itself prints the MPL figure, so do not treat the plan as a substitute for that check.
For a reconstruction, the platform of a typical landed house is assessed under the Code’s “General Developments” category. The MPL must not be lower than 4.0m above Singapore Height Datum (SHD) along the southern coast, or 4.5m above SHD along the northern coast; or 300mm above the adjacent road or ground level; or any other level specified by PUB, whichever is the highest. Those platform levels should be shown on the first-storey plans. If the house has a basement, the minimum crest level at entrances, exits or openings to the basement of a general development must be at least 150mm above that MPL.
Some A&A works, partial reconstruction that does not rebuild the first storey, and conservation projects need not comply with the required MPL, provided they have no direct or indirect linkages to underground special facilities. Even then, the QP is to advise the owner that the MPL is still recommended. A full rebuild is a reconstruction and is expected to comply. In low-lying areas, URA also measures building height from the MPL, as noted in our guide to plot ratio for landed houses.
PUB’s Quick Guide to Development Control (DC) advises developers and owners to purchase the DIP within six months before DC submission, so the latest drainage information is used. On the INLIS PUB Plans page, PUB also states that the QP need not apply for infrastructure plans for A&A that does not increase the existing building coverage area. A rebuild or reconstruction does not fall under that note.
Who Can Buy the Plans
PUB’s 31 July 2026 circular on the sale of these plans is addressed to owners, developers, architects, engineers, contractors and builders. The official INLIS user guide requires a Singpass login before you can search and buy.
The owner’s QP usually buys the plans, because the QP has to use them in the design and in the DC submission to PUB. A homeowner with Singpass can also purchase a set, for example when checking a plot before buying a house to rebuild, but that does not replace the QP’s duty to obtain current plans and verify them on site. Our guide to buying a landed house to rebuild sets out the other checks to make alongside these utility plans.
How to Buy a Sewerage Interpretation Plan Singapore and a DIP on INLIS
PUB Services Plans, including the SIP, DIP and WSP, are obtained from SLA INLIS. From 1 August 2026, PUB’s circular confirms that the plans are also available in Geographic Information System (GIS) format, as a geodatabase (GDB) file sold together with the PDF. You can choose PDF only, or PDF and GDB. The official user guide is at PUBUserGuide.pdf.
Older PUB advisories still point to earlier INLIS web addresses. Use the current portal in the 31 July 2026 circular: https://app.sla.gov.sg/inlis/#/home. The plans are not purchased through CORENET or CORENET X, which are for the QP’s later regulatory submissions.
The official INLIS user guide sets out these steps:
- On the INLIS homepage, open Borehole and Utility Information, then choose PUB Plans.
- Log in with Singpass, either in the Singpass app or with your Singpass username and password.
- Search with a key such as the address or the land lot. The PUB Plans page also has fields for postal code, road name, building name, and level and unit number where those apply.
- On the product details page, choose the Plan (SIP, DIP, and WSP if needed), the Type (PDF, or PDF and GDB), the Purpose and the Project Type. You can preview the plans before buying. There is also a map search: once the map is zoomed in to a scale of less than 1:10,000, you can select the lots on the map.
- Add the product to the cart, proceed to checkout, fill in the billing and contact information, accept the INLIS terms, and confirm the purchase.
- Complete payment. The confirmation page shows the purchase order (PO) number. Open View Purchase History / Download Products; when the file is ready, INLIS sends an email and the download arrow changes from blue to green.
If you choose PDF and GDB, each selected plan type comes with an explanatory note and a geodatabase zip file.
As of 19 November 2026 (Asia/Singapore), the SLA INLIS product listing shows “PUB Plans” at S$3.55. On the product page, that figure is labelled as a unit price including GST. Confirm the payable amount in your cart, because the total can depend on the lots and plan types you select. INLIS does not state a fixed delivery time. Wait for the email and the green download arrow rather than assuming the file is instant.
For the later DC submission to PUB, the INLIS PUB Plans page tells the QP to use the purchase order number (in the form X#######X) as the Receipt No., and “the date QP received SIP/DIP from PUB officer” as the Date of SIP/DIP. That wording may predate the current self-service download. Ask your QP to confirm how that date is recorded now that the plans are downloaded from INLIS.
What to Do After You Have the Plans
Give the SIP and DIP to your architect and engineers, and let them commission the site survey to confirm invert levels, the actual sewer alignment, the last connection point, and any common drain that the DIP does not show. If works later uncover a live or abandoned sewer or pumping main that is not on the SIP, PUB’s advisory says to contact PUB (Water Reclamation Network) at once.
Keep the DIP current. If DC submission slips more than six months after the purchase, PUB’s DC guide advises buying a fresh DIP. During construction, keep a copy of the SIP on site and do not start specified activities inside the public sewer corridor until PUB’s written clearance is in hand.
These plans are only one part of a rebuild. The house still has to sit inside URA’s envelope, and the works still have to reach Temporary Occupation Permit (TOP) and Certificate of Statutory Completion (CSC). See our house reconstruction page and our guide to the costs of building a landed house.
Frequently Asked Questions
Is a sewerage interpretation plan Singapore the same as an SIP?
Yes, in substance. Sewerage interpretation plan is the older name. PUB now officially calls it a Sewerage Information Plan (SIP). It shows the location and alignment of public sewers or pumping mains near the development. Existing sewer connections may not be shown and must be verified on site.
What does a Drainage Interpretation Plan show?
A DIP indicates drainage reserves or land reserved for future drainage schemes. It may not show the common drain on the plot. The QP should verify common drains on site and ascertain the Minimum Platform Level for effectual surface water drainage.
Who can purchase SIP and DIP plans?
PUB’s circular is addressed to owners, developers, architects, engineers, contractors and builders. INLIS requires a Singpass login. The QP usually buys the plans for design and DC submission, but a homeowner with Singpass can also buy them.
How do I buy SIP and DIP plans, and how long do they take?
Buy them on SLA INLIS under Borehole and Utility Information, then PUB Plans. Search by address or land lot, choose the plan types and format, pay, and download from Purchase History when INLIS emails that the files are ready. PUB and SLA do not state a fixed delivery time.
How much do SIP and DIP plans cost?
The SLA INLIS product listing showed PUB Plans at S$3.55, labelled as a unit price including GST, on 19 November 2026. Confirm the amount in your cart at the time you buy, as the payable total can depend on the lots and plan types selected.
Do I need both plans for a rebuild, and for A&A?
For a rebuild or reconstruction, yes. The SIP must be obtained before design, and PUB advises purchasing the DIP within six months before DC submission. For A&A that does not increase the existing building coverage area, PUB states on INLIS that the QP need not apply for infrastructure plans. Your QP should confirm whether that note applies to your proposal.
Will the SIP show my private inspection chambers?
Not necessarily. The SIP shows public sewers or pumping mains nearby, and existing sewer connections may not be shown. Private inspection chambers on your own drain-line have to be confirmed on site and shown on the drawings your QP submits.
Get the Plans Before the Design Is Locked In
At Three E Building Construction, we build landed home rebuilds, extensions and A&A works. We work with your architect and engineers so the layout, platform levels and site work respect the public sewers and drainage reserves shown on the SIP and DIP. If you are planning a landed house, talk to 3E Build. Builder with Integrity.