Every landed renovation starts with one question: “Do I need approval for this?” In Singapore there are usually two separate approvals to think about. The Urban Redevelopment Authority (URA) looks at planning: size, siting and use. The Building and Construction Authority (BCA) looks at building control: whether the works are safely designed and built. A project can need one, both, or neither.
Both sets of rules changed on 1 April 2025. URA widened the cases where your Qualified Person (QP) can simply lodge plans instead of applying for planning approval, and BCA rewrote its list of minor works that do not need plan submission. This guide explains landed house renovation approval in Singapore under the current rules.
URA Planning Permission: What Needs It and What Doesn’t
URA’s guide for land-titled residential properties gives homeowners a practical list. According to URA, planning permission is not required for:
- enlarging existing rooms, or relocating rooms if the primary residential use does not change;
- replacing or changing windows and doors, if there is no increase in gross floor area (GFA), no reduction in setback, and the window position does not change;
- re-constructing a roof in its existing form with no increase in height;
- gates, walls, fences or other enclosures, including boundary walls, not higher than 1.8m;
- a meter compartment not larger than 0.9m wide by 0.6m deep that forms part of the boundary wall;
- changing the shape of a swimming pool, if the pool does not get bigger and existing setbacks are not reduced; and
- converting a car porch roof into an open balcony or garden, if the parapet wall is not higher than 1m, the parapet is visually porous (such as tempered glass or metal railings), and any lightweight screen wall along the common boundary is not higher than 1.8m.
Planning permission is required for:
- closing up an open balcony (approved “covered balconies” that already comply with setbacks can be closed with glass panels or windows without planning permission);
- all proposed earthcut and earthfill;
- a new pavilion; and
- redeveloping one landed property into more than one.
Note the earthworks rule: cutting or filling ground is often part of a garden, driveway, swimming pool or basement project, so raise it with your QP early.
A&A, Reconstruction or New Erection? URA’s 50% Tests
Once a project goes beyond the simple cases above, URA classifies it. URA’s Additions and Alterations to Landed Housing handbook says a proposal qualifies as additions and alterations (A&A) only if:
- the additional GFA does not exceed 50% of the approved GFA;
- external walls removed and replaced with new walls do not exceed 50% of the approved external walls;
- structural changes (such as new or replaced columns and beams, or reconstructed floor slabs) do not exceed 50% of the existing building;
- any change or replacement of the entire roof does not involve an additional storey; and
- any added attic keeps the GFA increase within the limit.
Proposals outside these criteria are treated as reconstruction. URA also deems two outcomes to be reconstruction regardless of the 50% figures: an increase in storey height (including roof changes that add a storey), and a change in housing form, for example from a semi-detached house to a bungalow. The explanatory notes to URA’s Form DC 6 add that works involving demolition of the entire dwelling house are regarded as a new erection.
If you are weighing a big renovation against a full rebuild, our guides on GFA vs built-up area and buying a landed house to rebuild explain the related terms.
What Changed on 1 April 2025: URA Plan Lodgment
Under URA’s Plan Lodgment Scheme, qualifying A&A or new erection proposals for a single landed house do not need to apply for planning approval. Your QP lodges the plans and declares compliance, and planning approval is deemed granted under the terms of the lodgment.
URA circular DC25-05, effective 1 April 2025, relaxed the criteria in two main ways:
- Where it applies: lodgment used to be limited to existing landed houses within Designated Landed Housing Areas. It now covers existing landed houses on land zoned Residential in the Master Plan. Conservation Areas and Good Class Bungalow Areas remain excluded.
- Deviations: previously, the whole proposal had to fully comply with prevailing guidelines. Now, new structures that deviate can still be lodged if the QP first obtains URA’s approval for the deviation through a waiver application. Existing approved structures that do not meet current guidelines can be retained with a Professional Engineer’s (PE) certification, subject to URA’s retention requirements.
Those retention requirements, set out in the handbook and on URA’s lodgment criteria page for A&A to a landed house, include retaining at least 25% of the existing floor plate as an integrated wing that includes the non-conforming portion, and, for a house with a deficient front setback, a minimum absolute 2.4m setback from the front boundary.
Other lodgment criteria to check
The lodgment page lists further conditions. The site must not be in a Special Control Area (URA directs QPs to check this on URA SPACE), the plot must not be affected by road or drain widening proposals, no part of the plot can be State land, the vehicular access arrangement must not change, the house type must stay the same, and no part of the house being retained can consist of unauthorised works. Any proposed earthfill must not raise any point in the plot by more than 1m.
Your QP should confirm against the full list whether your plot qualifies for lodgment or needs a full application.
BCA: Works That Don’t Need Plan Submission
BCA calls these “insignificant building works”. They are listed in the First Schedule of the Building Control Regulations 2003, which was substantially rewritten by the Building Control (Amendment) Regulations 2025 from 1 April 2025. Items relevant to landed homes include:
- Lean-to extensions: any single storey lean-to extension with a roof covering of tiles, or of any lighter material, in a bungalow, semi-detached, terrace or linked house.
- Shelters: a single storey shelter on the ground or on an existing reinforced concrete roof, up to 10 square metres if it has no safety barriers. Up to 50 square metres is allowed in a private space of a residential building if beam spans are within 6m, cantilevers within 3m, the sides are lightweight material, windows or doors that do not act as safety barriers, and the roof is lightweight.
- Boundary walls, fences and gates that are not load bearing.
- Retaining walls not on piled foundations and not within 3m of another retaining structure, with a visible height of up to 1.5m in steel or reinforced concrete, or up to 1m in other materials.
- Lofts with only timber flooring and no larger than 5 square metres, and the removal of timber or steel lofts.
- False ceilings of lightweight material suspended from the structural ceiling, used solely for aesthetic purposes, not accessible to anyone, with no supporting span over 6m.
- Partitions up to 10m high. In landed houses, any non-laminated glass in the partition must not be more than 2.4m in height (see the note below).
- Enclosing the sides of a balcony, yard or terrace with windows and glass panels; replacing windows and doors; replacing floor and wall finishes; and all air-conditioning works.
Note on the glass partition rule: the 2025 amending regulations say “from the ground”, while the consolidated First Schedule on Singapore Statutes Online reads “above the floor level”. Your QP should confirm how this applies to an upper-floor partition.
Note the overlap: BCA may not need plans for enclosing a balcony with glass, but URA requires planning permission to close up an open balcony. As BCA’s guide to building works not requiring approval puts it, even when BCA plan approval is not necessary, homeowners must still observe safety and good practices, and obtain the approvals required by other authorities such as URA.
BCA Exemptions for Owner-Occupied Landed Houses
For works that do need BCA approval, BCA’s page on exemptions for building works requiring approval lists some design flexibility for landed houses built for the owner’s own use:
- Headroom and ceiling height: the requirements do not apply to attics of 10 square metres or less in such houses, or to toilets and bathrooms in them.
- Staircases: the requirements for handrails, landings, and minimum width, tread and riser do not apply.
- Safety barriers: the requirements on barrier height, gaps and climbability do not apply.
- Light and ventilation: natural lighting and natural ventilation are not required, so owners may use artificial lighting and mechanical ventilation or air-conditioning.
“Exempt” does not mean a steep stair or low railing is safe for young children or elderly parents, so discuss these choices carefully with your QP.
Unauthorised Works From the Past
BCA suggests comparing the as-built house with the approved plans, which you can buy from BCA, and says owners found with unauthorised additions or alterations face enforcement under the Building Control Act. URA’s lodgment criteria also exclude retaining unauthorised works. If you want to keep such works, BCA advises engaging a QP to submit plans for approval and obtain other necessary approvals, such as from URA.
Questions to Ask Your QP or Builder
- Does my plan count as A&A, reconstruction or new erection under URA’s tests?
- Does my plot qualify for URA plan lodgment, or is a full application needed?
- Is my site in a Conservation Area, Good Class Bungalow Area or Special Control Area, or affected by road or drain widening?
- Are there existing structures that don’t match the approved plans?
- Which of my works need BCA plan submission, and which are insignificant building works?
Frequently Asked Questions
Do I need URA approval to renovate the inside of my landed house?
Not for enlarging existing rooms, or relocating rooms without changing the primary residential use, according to URA. Works that add floor area, change the outside of the house or involve earthworks may need planning permission or lodgment.
Is adding a storey to my house treated as A&A?
No. URA deems any increase in storey height to be reconstruction, regardless of whether the works exceed 50% of the existing building GFA. Demolishing the entire house is regarded as a new erection.
What did URA change on 1 April 2025?
Under circular DC25-05, plan lodgment now covers existing landed houses on land zoned Residential, not only Designated Landed Housing Areas. Conservation Areas and Good Class Bungalow Areas are still excluded.
Does a rear lean-to extension need BCA plan submission?
Under the First Schedule as amended from 1 April 2025, a single storey lean-to extension with a tiled or lighter roof covering in a landed house is an insignificant building work. URA and other clearances may still apply.
If BCA approval isn’t needed, can I start work straight away?
Not necessarily. BCA says homeowners must still obtain approvals required by other authorities such as URA, and observe safety and good practices. Ask your QP to check all clearances first.
Plan Your A&A With a Builder Who Works Alongside Your QP
At Three E Building Construction, we build landed home extensions, A&A works and rebuilds, working with your architect and engineers so approvals and site work line up. If you are planning changes to your home, talk to 3E Build about your project before you finalise the design.
Sources (the URA, BCA and Singapore Statutes Online pages linked above) checked on 10 November 2026 (Singapore time). General guidance only, not professional advice. Your QP or architect must assess your specific site.