CORENET X Singapore: What It Means for a Landed House Rebuild or A&A

If you are planning a landed house rebuild or addition and alteration (A&A) works, you may have heard that CORENET X becomes compulsory from 1 October 2026. That date is real. It does not, however, automatically apply to every landed house.

A joint Building and Construction Authority (BCA) and Urban Redevelopment Authority (URA) circular dated 23 July 2026 updated the rollout. From 1 October 2026, the Gateway Processes are mandatory only for new projects with a gross floor area (GFA) of 5,000m² and above. Projects below that threshold may continue to use CORENET 2.0 for now. This article follows official BCA, URA and related agency sources checked on 23 November 2026. It does not invent fees or typical approval times. The official pages do not publish those figures for a landed house.

What CORENET X Is, and How It Differs from CORENET 2.0

CORENET X is Singapore’s one-stop digital shopfront for regulatory approvals of building works. BCA and URA lead it, with support from GovTech and other agencies. Those agencies include the Land Transport Authority (LTA), the National Environment Agency (NEA) and the National Parks Board (NParks). They also include the Public Utilities Board (PUB), the Singapore Civil Defence Force (SCDF) and the Singapore Land Authority (SLA). The platform was soft-launched on 18 December 2023. Official materials are on the official website, also reached via go.gov.sg/cx.

Under CORENET 2.0, a project team typically sends separate submissions to different agencies. Official guidance says building projects often go through more than 20 approval touchpoints. The team then receives responses separately. Consultants can also be working off different versions of the plans.

The new process changes that model. Qualified Persons (QPs) first coordinate the design. They then submit a single coordinated model. Agencies review that model together and issue a consolidated response. The new Regulatory Approval for Building Works (RABW) streamlines those many touchpoints into three main sequential gateways. These are the Design Gateway, the Construction Gateway and the Completion Gateway. There is also an optional Piling Gateway. Simpler typologies can use a Direct Submission Process (DSP) instead.

The official comparison with CORENET 2.0 also sets out practical differences. The submission portal is web-based. Teams therefore do not need to download a separate application to prepare a filing. Appointment of project members is digital. Payment is part of the application. Processing starts only after the relevant fees have been paid and verified. Homeowners appear in the system as “Developer (Individual)”. Licensed builders and other project members also log in. In addition, all members can view submissions made under the project.

Is CORENET X Mandatory for a Landed House?

This is the question most owners ask. The current official answer is based on GFA. It is not based on whether the project is a landed house.

The 23 July 2026 joint circular (BCA APPBCA-2026-12, URA/PB/2026/08-DCG) sets out the revised plan. So does URA’s Development Application page, last updated on 30 September 2026. The requirements are as follows:

  • New projects with GFA of 30,000m² and above must use the Gateway Processes from 1 October 2025. This phase is already in force.
  • New projects with GFA of 5,000m² and above must use those Gateway Processes from 1 October 2026.
  • Ongoing projects with GFA of 5,000m² and above that had already started CORENET 2 submissions by 30 September 2026 may continue in CORENET 2 for now, until further details are announced.
  • All projects with GFA below 5,000m² may use the Gateway Processes on a voluntary basis. Submissions may continue through CORENET 2 for now.

Gateway Processes, in this circular, include both the three-gateway process and the Direct Submission Process.

“New projects” means new buildings, or works to existing buildings, that have not yet been formally submitted. That formal step is a Development Application to URA, or a Development Control application to a regulatory agency such as LTA, NEA, NParks or PUB. The mandatory rule then applies specifically to three cases:

  1. erection of building(s) with a total GFA of 5,000m² or more;
  2. additions or extensions that create an additional GFA of 5,000m² or more; or
  3. major addition and alteration works with an affected or replaced GFA of 5,000m² or more.

Official sources do not publish a typical GFA for a single-unit landed house. They also do not exempt “landed houses” as a class. Therefore, you should ask your QP to confirm the project’s GFA against this threshold. Our guide to GFA versus built-up area explains how GFA is measured for a landed house.

Some older pages still describe the earlier plan. That includes a few URA lodgment pages last updated before this circular. The earlier plan would have made the Gateway Processes mandatory for all new projects from 1 October 2026, regardless of GFA. The 23 July 2026 circular superseded that approach for projects below 5,000m². Use the joint circular and URA’s 30 September 2026 Development Application page when you check the current rule.

BCA’s 22 July 2026 media release explains why the plan was recalibrated. Agencies found that the benefits are more significant for larger and more complex projects. Smaller projects generally involve fewer agencies. They are also often undertaken by smaller firms. For those projects, BCA said the costs of mandatory adoption may outweigh the benefits. The circular also says agencies are working to streamline the existing submission process for this smaller tier. They will share more details when ready. Project teams that are keen and ready may still use the new portal voluntarily. Official guidance says they will be supported.

If Your Project Uses the New Portal: The Direct Submission Process

If your team does use the new portal, you will not necessarily go through all three gateways.

The official site says the Direct Submission Process (DSP) is the default application process for single-unit landed houses. DSP is a single-stage approval before Temporary Occupation Permit (TOP) or Certificate of Statutory Completion (CSC). It therefore skips the Design Gateway, the optional Piling Gateway and the Construction Gateway. The July 2026 circular likewise lists single-unit residential landed properties as an example of smaller-scale projects eligible for DSP. Teams can still hold pre-submission consultations with agencies first.

URA’s Plan Lodgment Scheme

Within DSP, URA’s Plan Lodgment Scheme may apply. This covers qualifying A&A works, or a new erection, to an existing single landed house. The QP can lodge the plans with URA and declare that they comply with the prevailing development control guidelines and lodgment criteria. Planning approval is then deemed granted. The official DSP page says an existing landed house on land zoned Residential in the Master Plan qualifies. Conservation Areas and Good Class Bungalow Areas (GCBAs) are excluded. Lodgment is for works to an existing single landed house with its own land title. That means one house within one lot.

URA’s additions and alterations to a landed house lodgment page, last updated on 13 July 2026, sets out a longer list of criteria. Among other points, the proposal must not sit in a Special Control Area. It must also comply with Envelope Control guidelines. For A&A, added GFA must not exceed 50% of the existing and approved GFA. Replacement of external walls must not exceed 50% of the existing and approved external walls. Structural changes must not exceed 50% of the existing and approved floor area. If the proposal cannot meet those A&A tests, URA says it should be lodged as a new erection or reconstruction proposal. A QP must be appointed for the works. See our guides to envelope control and landed house renovation approval for the planning rules themselves.

When lodgment does not apply

Applications that do not qualify for lodgment go through a single-stage plan check. The official DSP page says that includes conserved houses and good class bungalows. Those proposals are assessed on the merits of their design and site context. Applications involving two or more houses, if submitted through the new portal, are processed through the three-gateway RABW, not DSP.

The Three Gateways, When They Apply

The three-gateway process is the default RABW path for building projects that are not on DSP. At each gateway, coordinated Building Information Modelling (BIM) submissions from the various disciplines are reviewed collectively by the agencies. The aim is to surface and resolve cross-agency issues early, before construction.

The official 3-Gateway Process page sets out the milestones as follows.

Design Gateway

This gateway is meant to settle key parameters that affect the design and the client’s brief, before detailed design proceeds. Key approvals include URA Provisional Permission, LTA, NEA and PUB Development Control clearances, and NParks DC approval.

Piling Gateway, which is optional

Teams that want to start piling and foundation works before Construction Gateway approval can use this optional gateway. It covers items such as pile caps, raft foundations, and earth retaining and stabilising structures. It does not cover superstructural works. Key approvals include BCA structural approvals for permanent piling works. Where the site is in a railway protection zone, it also includes LTA in-principle approval for the pile design and pile layout plan.

Construction Gateway

This gateway is meant to settle coordinated design details before main structural works start, and before a sales launch. Key approvals include URA Written Permission and BCA building plan and structural approvals. They also include, where relevant, LTA street plan, parking and railway building-plan clearances, NEA and PUB building-plan clearance, and SCDF building-plan approval.

Independent submissions and the Completion Gateway

Some agency-specific submissions can run in parallel, because they have no cross-agency dependencies. Official examples include NParks tree-felling approval and PUB Earth Control Measures approval. Each agency publishes its own expected response time for these independent items.

The Completion Gateway documents as-built plans. It is used to obtain the occupancy permit or statutory completion. The QP first obtains technical clearances from the relevant agencies. That step may involve site inspections or certifications of supervision. Once those clearances are in, the appointed Project Coordinator applies to BCA for the overall TOP or CSC.

BIM submissions in IFC+SG format are mandatory for new erections or major A&A with new GFA of 5,000m² or more. URA’s submission page, last updated on 30 September 2026, also states the format for smaller projects. For projects below 5,000m², 2D format or lightweight BIM are allowed. IFC+SG is the openBIM Industry Foundation Classes standard, with Singapore additions for local regulatory needs. QPs must follow the current Code of Practice. The official COP page states that COP Fourth Edition takes effect for new gateway and amendment submissions from 1 January 2027.

Who Submits, and What the Owner Should Ask

Owners do not submit the plans themselves. URA states that only QPs with a valid Practising Certificate can submit a Development Application through the new portal. That includes registered architects, professional engineers and registered surveyors. The QP’s statutory obligations remain in place.

That does not mean the owner is absent from the process. The developer appoints project members digitally. For a homeowner, that role is “Developer (Individual)”. The Project Coordinator needs a clear picture of which professionals are involved, so that appointments and forms are complete. A licensed builder is also a project member who logs in. For joint submissions, official guidance says a lead QP should coordinate. The member who starts the submission is treated as the submission coordinator.

Before you sign off a design or a programme, ask your architect, engineers and builder these questions:

  • What is the project’s GFA, and does it meet the 5,000m² mandatory threshold?
  • Will the team submit through CORENET 2.0, or use CORENET X voluntarily?
  • If the new portal is used, will the project go through DSP, URA plan lodgment, a single-stage plan check, or the three-gateway process?
  • Who is the Project Coordinator, and which QPs will be appointed?
  • Which agency approvals apply to this plot, including PUB, NParks, LTA, SCDF and NEA?
  • How will demolition, if any, be sequenced with the planning and building-plan submissions?
  • Have early official checks been programmed, including the sewerage and drainage interpretation plans and, for an older house, an asbestos survey?

How Timelines and Fees Are Officially Described

Official pages do not publish a standard approval duration, or a standard submission fee, for a typical landed house rebuild or A&A. You should ask your QP for a project-specific programme and a fee estimate.

What the official sources do state is the service standard. They do not state a typical elapsed time for a whole project. The official submission workflows page states the service standard. Relevant agencies provide Written Directions or approvals after a service level agreement of up to a maximum of 20 working days. NEA’s service standards page says it is aligned with that service level agreement. It lists 20 working days for Design Gateway, Construction Gateway, Completion Gateway (TOP/CSC) and Direct Submission Process applications, including lodgment. That period runs from the date a full set of documents is received. BCA’s overall TOP and CSC applications are processed within 7 working days upon submission of complete documents. Express TOP applications, if accepted by BCA, are processed within 1 working day upon complete documents and receipt of payment. Independent submissions have their own stated response times, which differ by agency.

Processing starts only after the relevant fees have been paid and verified. Official pages checked on 23 November 2026 do not publish a standard fee for a landed house under either portal. URA points lodgment applicants to its Development Control Fee Schedule for lodgment fees. Ask your QP to compute the fees for your project.

The 23 July 2026 circular reports progress since mandatory implementation for large projects from 1 October 2025. More than 140 projects involving 300 firms had made submissions through the new platform. It also says those projects had achieved time savings of up to two months, with cost savings from reduced abortive work. That is an official agency figure from those early projects. Those were the larger developments already required to use the new process. It is not a published typical saving for a single-unit landed house.

Demolition may take place before other regulatory submissions for the new house. If so, official guidance says the demolition filing is a joint submission to BCA and URA, with payment of the applicable fees. BCA will approve that demolition only where URA also approves the demolition, or has authorised or approved the redevelopment of the site.

Frequently Asked Questions

Is CORENET X mandatory for my landed house rebuild or A&A from 1 October 2026?

Only if the project is a new project with GFA of 5,000m² or more, as defined in the 23 July 2026 joint BCA-URA circular. Projects below 5,000m² may continue to use CORENET 2.0 for now. Ask your QP to confirm the project’s GFA, because official sources do not exempt landed houses as a class.

Who submits the plans, the owner or the QP?

Only a QP with a valid Practising Certificate can submit a Development Application through the new portal. That person will be a registered architect, professional engineer or registered surveyor. The owner does not file the plans. A homeowner can, however, log in as Developer (Individual) for digital appointment of project members.

If we use the new portal, do we go through all three gateways?

Not for a typical single-unit landed house. The official site says DSP is the default process for single-unit landed houses. DSP is a single-stage approval before TOP or CSC. Applications involving two or more houses, if submitted through the new portal, go through the three-gateway process.

Does a conserved house or a good class bungalow use the same process?

If the team uses the new portal, conserved houses and good class bungalows may not qualify for URA plan lodgment. Those cases are processed under a single-stage plan check. They are assessed on the merits of their design and site context. URA’s Plan Lodgment Scheme excludes Conservation Areas and GCBAs.

Do I still need SIP, DIP or an asbestos survey if we use the new portal?

Yes, where those duties already apply. The new platform is a submission process. It does not replace PUB’s sewerage and drainage interpretation plans, or MOM’s asbestos survey rules for older buildings. Programme those checks with your QP and builder before demolition is booked.

How long does approval take, and how much are the fees?

Official pages checked on 23 November 2026 do not publish a standard duration or a standard fee for a landed house rebuild or A&A. The published service standard for gateway and DSP responses is up to a maximum of 20 working days after complete documents are received. BCA processes complete TOP or CSC applications within 7 working days. Processing starts only after the relevant fees have been paid. Ask your QP for a project-specific programme and fee computation.

Can my project team choose the new portal even if the GFA is below 5,000m²?

Yes. The 23 July 2026 circular says submissions for projects below 5,000m² may continue through CORENET 2 for now. However, project teams that are keen and ready to use the Gateway Processes are encouraged and will be supported. Agencies have also said they will share more details later on a streamlined approach for this tier.

Plan the Submission Path Before Demolition Is Booked

At Three E Building Construction, we build landed home rebuilds, extensions and A&A works. We work with your architect and engineers so the submission path sits in the right order with the site works. That applies whether the team uses CORENET 2.0 or the new portal. If you are planning a landed house, talk to 3E Build. Builder with Integrity.